Project Update Huisman Global ServicesDecember 22, 2010Semi 2: Replacement of Slew bearing, Aux and Topping Winches and the Tugger HPU on the 225mt OMC Client: Mantenimiento Marino de Mexico Project Manager: Edwin Slop
In March 2011 HGS will start with the replacement of the slew bearings, auxiliary and topping winches and the tugger HPU in Tampico, Mexico. Due to the current condition of the 225mt Offshore Mast Crane onboard the Semi 2 a large update and overhaul is needed. The jib, masthead and slewing platform will be removed from the crane. The jib will be blasted and repaired by our Client Mantenimiento Marino de Mexico under supervision of Huisman. Huisman will replace the slew bearings by removing the slew platform of the mast and exchanging this on the quay. When the slew platform is on the quay, the tugger HPU will be replaced by a brand new HPU, which is built at HK.
In the winch room all hydraulic and electrical lines will be replaced. To replace the auxiliary and topping winch a hole will be cut at the location of the pedestal entrance door.
The project must be finished in Q2 2011. |
News – Huisman Global ServicesSeptember 06, 2011 450mt Hang-off Module and Upgrade J-Lay tower Seven Seas December 22, 2010 Project Update Huisman Global Services March 25, 2010 Huisman Global Services at OTC 2010 Huisman Intrepid ServicesTo locally support the North American market, Huisman opened a Sales and Engineering office in Houston, Texas, USA.
Huisman US, Inc United States of America |